Gas Engine Experiences

실적
Kyongbang Pill Dept. Store 1600KW 6.6KV*3set parallel kepco panel, test, cogeneration control, NGR. electric work, HMI, commissioning test. CATERPILLAR
Cheonan chungsu area 8400KW 6.6KV*2set parallel kepco panel, test, cogeneration control, mcc. electric work, commissioning test. WARTSILA
Yeoido IFC B/D 1600KW6.6KV*1set parallel kepco panel, cogeneration control, NGR. electric work, HMI, commissioning test. CATERPILLAR
Bundang bus terminal 1300KW 6.6KV*3set automatic control Electic work, commissioning test. WARTSILA
Seoul city 350KW6.6KV *2set parallel kepco panel, cogeneration control, mcc. electric work, test. MCC. NGR. HMI, commissioning test. CATERPILLAR
Nanji gas cogeneration(Korea heating cop.)1500KW 6.6KV*2set gas engine radiator control, MCC, parallel kepco panel, commissioning test, cogeneration control MWM
Gas tech. Oksu apt 450KW 380KV*2set gas engine radiator control, MCC, parallel kepco panel, test, cogeneration control. NGR. HMI MWM
Gas tech. Daejeon apt 800KW 380KV*1set gas engine, control, MCC, parallel kepco panel, test, cogeneration control. NGR.HMI MWM
Cheonan Dankuk Univ. Hospital 80KW 380KV*1set gas engine, MCC, parallel kepco panel, commissioning test, cogeneration .NGR WAUKESHA
Daegu sinchun 800KW 380KV*2set gas engine, MCC, parallel kepco panel, commissioning test, MCC WAUKESHA
Jecheon a sewage disposa plant 280KW380KV*1set gas engine control, MCC, parallel kepco panel, commissioning test, cogeneration WAUKESHA
Gimpo landfill 400KW 380KV*2set gas engine control, MCC, parallel kepco panel, commissioning test. DOOSAN
Gimpo landfill 400KW3 80KV*3set gas engine control, MCC, parallel kepco panel, commissioning test. DOOSAN